Schedule: November 8th Cleaning and Road Building Commenced
 
A: Administrative and Common Area

     1.Foundation- Work will start the end of December with completion scheduled for the end of March 2005

     2.Roofing-  To be completed by end of July 2005

     3. Interior Work- To be complete mid May 2005

 
B: Two Story Classroom Wing

     1. Foundation- To be completed mid April 2005

     2. Roofing- To be completed mid September 2005

     3. Interior Work-To be completed mid June 2006

 
C: Gymnasium

     1. Foundation- To be completed June 2005

     2. Roofing- To be completed end of October 2005

     3. Interior Work- To be completed mid July 2006

 
D: Performing Arts and Auditorium

     1. Foundation- To be completed mid May 2005

     2. Roofing- To be completed mid September 2005

     3. Interior Work- To be completed end of May 2006

 

Last Update: March 31, 2005