Preliminary Work Plan
Cony High School

Activity Name Proposed Date

Completed

SITE ANALYSIS STUDIES Jan -Mar 2002 X
REVISED SITE MASTER PLAN Jan - June 2002 X
STATE FUNDING ANNOUNCEMENT Mar 2002 X
EDUCATIONAL VISION Mar - Aug 2002 X
TEACHER PRESENTATIONS April & Sept 2002 X
TEACHER INTERVIEWS Sept 2003 X
PUBLIC INPUT MEETINGS Sept, Nov 2002 & Jan 2003 X
SCHOOL DEPT. INPUT July - Oct 2002 X
PRINCIPLES OF ORGANIZATION Aug - Oct 2002 X
EDUCATIONAL SPECIFICATIONS & SPACE PROGRAM Aug - Oct 2003 X
CONCEPT SITE PLAN June - Dec 2002 X
CONCEPT BUILDING PLAN Sept - Nov 2002 X
COST ESTIMATES Oct & Dec 2002 X
SITE ACQUISITION OPTIONS Sept - Dec 2002
DOE APPENDIX "B": BUILDING June - Sept 2002
DOE APPENDIX "C": SITE June - Sept 2003
ENROLLMENT STUDIES July - Sept 2002 X
DOE PROGRAM CONFERENCE: "B", "C" & ENROLLMENT Feb 2003
AUGUSTA PLANNING BOARD Aug 2003
DOE SITE REVIEW Aug 2004
PUBLIC HEARING: SITE Mar 2003
SBOE APPROVAL: SITE June 2003
DOE PROGRAM APPROVAL March 2003
DOE CONCEPT DESIGN REVIEW June - Aug 2003
COST ESTIMATES Aug 2003
PUBLIC HEARING: STRAW VOTE Sept 2003
DEP APPROVAL Oct 2003 - Mar 2004
SBOE CONCEPT APPROVAL Sept 2003
FIRE MARSHAL APPROVALS June 2003
AUGUSTA PLANNING BOARD APPROVAL Dec 2003 - Mar 2004
PUBLIC EDUCATION Sept - Nov 2003
REFERENDUM Nov 2003
DESIGN DEVELOPMENT: CONTRACT II Nov 2003
DESIGN DEVELOPMENT Oct 2003 - Mar 2004
COST ESTIMATES Feb 2004
DOE DD APPROVAL Mar 2004
SBOE APPROVAL Aug 2004
FUNDING APPROVAL Aug 2004
EARLY SITE CONTRACT July - Dec 2004
SELECT OWNER'S REP. Mar 2004
CONSTRUCTION DOCUMENTS April - Aug 2004
COST ESTIMATES Aug 2004
DOE / BGS REVIEW Aug - Oct 2004
BID Nov 2004
AWARD Dec 2004
CONSTRUCTION (17 MONTHS) Jan 2005 - Aug 2006
RENOVATION June - Dec 2006 
BONDING: 2006 May 2006
OCCUPANCY: SEPT. 2006 Sept 2006
RENO. OCCUPANCY: JAN. 2007 Jan 2007

Last Update: April 26, 2005